Building predictable delivery at scale

CoreCard, a major US consumer card programme: a delivery structure and cadence where dates are fixed up front and only work that fits is committed.

In flight
Year
2019
Type
Programme
Headline
7 teams · 104 people one delivery structure and cadence

Context

When I joined CoreCard in 2019, the programme had no established PMO and no consistent Agile operating model. Teams were organised by function and product, serving a major US consumer card programme.

I set up a delivery structure and cadence across 7 teams and 104 people.

What I did

  • Led release planning, cross-team scheduling, estimate validation, dependencies and escalations.
  • Reconciled customer commitments with engineering capacity.
  • Ran release governance, billing validation and delivery traceability.
  • Became the primary lead for customer delivery discussions within about 6 months, working with 10–15 customer product owners and the relevant service leads.

Operating model

  • Customer deliveries every 2 sprints (about 4 weeks), later every 4 sprints (about 8 weeks).
  • Delivery dates fixed up front. Only work that could realistically fit was committed; the rest was reprioritised or moved to a later delivery.
  • High-priority defects closed before release.

The result was a planning and release model the customer could rely on.

A major programme within the same card-platform engagement

  • 2–3 months of proposal and sizing, and involvement from proposal through planning and execution.
  • Coordinated engineering and QA estimates and sizing.
  • Contributed to the financial proposal.
  • Took part in senior client discussions to explain and defend the proposed numbers. The final commercial figures were vetted by the COO.
  • At its peak, the programme had approximately 150 people across Development, QA and PMO.

Split to unblock

The customer needed an important deliverable in about 1 month; the engineering estimate was about 2. Working with the internal teams and the customer, we split the work: the critical scenarios shipped within the month, and the rest followed in parallel. That unblocked the customer without overcommitting the teams.

Delivery engineering

I don't treat a PMO as spreadsheets and meetings. Where delivery friction kept recurring, I removed it with a tool:

  • Customer-to-internal Jira sync. The customer's Jira and ours weren't connected; automation replaced the manual transfer between them.
  • A standard estimation template, so estimates from different teams could be compared and validated.
  • Generated release notes, instead of assembling them by hand for every delivery.
  • SVN pre-commit checks that enforce Jira traceability on every change.
  • Delivery analytics, later built out as Plotly Dash tooling.